Red Deer Regional Hospital Centre Redevelopment

Share Red Deer Regional Hospital Centre Redevelopment on Facebook Share Red Deer Regional Hospital Centre Redevelopment on Twitter Share Red Deer Regional Hospital Centre Redevelopment on Linkedin Email Red Deer Regional Hospital Centre Redevelopment link

We're building forward, together.

The Red Deer Regional Hospital Centre (RDRHC) Redevelopment Project (Project) is a $1.8-billion investment that will upgrade services throughout the hospital and add significant capacity.

There are two major components of this Project:

  1. construction of a new patient tower, and renovations and upgrades throughout the existing building
  2. construction of an ambulatory building (across 39th Street from the parkade)

Highlights of the Project and its components include:

  • the addition of 200 new beds in the patient tower.
  • six new operating rooms.
  • two cardiac catheterization labs.
  • an expanded Medical Device Reprocessing Department.
  • outpatient services, addiction and mental health, renal dialysis and underground parking at the ambulatory building

As the project progresses, programs, services and their equipment will be relocated within the site to accommodate construction and renovations.

The new patient tower and the ambulatory building will be completed before the finalization of the total redevelopment project, which is expected to be completed and fully commissioned by 2031.

We will be engaging you over the lifetime of this project, so please visit often or register to receive updates to your email.

We're building forward, together.

The Red Deer Regional Hospital Centre (RDRHC) Redevelopment Project (Project) is a $1.8-billion investment that will upgrade services throughout the hospital and add significant capacity.

There are two major components of this Project:

  1. construction of a new patient tower, and renovations and upgrades throughout the existing building
  2. construction of an ambulatory building (across 39th Street from the parkade)

Highlights of the Project and its components include:

  • the addition of 200 new beds in the patient tower.
  • six new operating rooms.
  • two cardiac catheterization labs.
  • an expanded Medical Device Reprocessing Department.
  • outpatient services, addiction and mental health, renal dialysis and underground parking at the ambulatory building

As the project progresses, programs, services and their equipment will be relocated within the site to accommodate construction and renovations.

The new patient tower and the ambulatory building will be completed before the finalization of the total redevelopment project, which is expected to be completed and fully commissioned by 2031.

We will be engaging you over the lifetime of this project, so please visit often or register to receive updates to your email.

  • Interim Cardiac Catheterization Lab Announcement

    Share Interim Cardiac Catheterization Lab Announcement on Facebook Share Interim Cardiac Catheterization Lab Announcement on Twitter Share Interim Cardiac Catheterization Lab Announcement on Linkedin Email Interim Cardiac Catheterization Lab Announcement link
    supporting image

    Through a Memorandum of Understanding (MOU) and anticipated donor support, cardiac catheterization will be available at Red Deer Regional Hospital Centre (RDRHC) sooner than expected.

    That was the announcement on October 18 (RDRHF Announces Cath Lab Opening 5 Years Ahead of Schedule (rdrhfoundation.com)) when the Red Deer Regional Health Foundation and Alberta Health Services (AHS) shared the news that they’ve signed an MOU to support construction of a temporary cardiac cath lab which is expected to be complete within 24-30 months.

    This will establish cardiac catheterization ahead of the RDRHC Redevelopment Project, which will see two permanent labs constructed. The two permanent labs will be constructed back-to-back and work together jointly, while the temporary one will be standalone.

    To create a home for the temporary cardiac cath lab, the existing physicians lounge at the hospital will be converted. Space will then be repurposed elsewhere in the facility to ensure physicians continue to have a quiet space to get away from the demands of the day.

    Preliminary design plans are already in place for the interim cardiac cath lab and through the MOU, the Foundation will be providing the financial support for the essential architectural, mechanical, and electrical upgrades.

    Once the two permanent cardiac cath labs are completed through the Redevelopment Project, the interim cardiac cath lab will be transformed into a Vascular and Neurology lab.

    By establishing an interim cardiac catheterization laboratory, AHS will be able to provide a new cardiac service to patients at RDRHC years sooner, which will help reduce the need for patients to travel to other facilities. This will also support our ongoing efforts to recruit and retain the talented healthcare professionals needed to provide care every day to our patients. We are continuing our efforts to expand the support services available to compliment the cardiac cath lab, including recruitment of additional cardiologists, and planning for more comprehensive cardiac rehabilitation.

  • Changes to parking, site access effective October 15, 2024

    Share Changes to parking, site access effective October 15, 2024 on Facebook Share Changes to parking, site access effective October 15, 2024 on Twitter Share Changes to parking, site access effective October 15, 2024 on Linkedin Email Changes to parking, site access effective October 15, 2024 link
    supporting image

    Patients and visitors to Red Deer Regional Hospital Centre (RDRHC) will notice changes to traffic flow and parking at the site, as work continues on both the parkade expansion and the hospital redevelopment.

    The three public entrances to the RDRHC site will be reduced to two:

    • Entrance from 50A Ave. remains open and will be one-way effective Oct. 15, with traffic exiting to 39 St. Please pay close attention to signage for public access.
    • Entrance from 39 St., accessed from the west off 52 Ave., remains open as the entrance closest to the public South Parkade.
    • Closed effective Oct. 15: The entrance from 52 Ave. between the West public parking lot and Central Alberta Cancer Centre (CACC) parking lot.

    As for parking changes at the site, the public should note that the West public parking lot will be closed, effective Oct. 15.

    A portion of the Central Alberta Cancer Centre (CACC) public parking lot will also be closed. Members of the public and site visitors are asked to please reserve this lot for patients of the CACC and their family members only.

    As a reminder, work on expanding the South parkade continues to necessitate the closure of 39 St. between 52 Ave. and 51 Ave. at this time. The parkade remains open for patients, public and staff parking while construction is underway.

    Signage and flag persons are on site to direct traffic. Motorists are asked to please slow down when driving through the site and obey directions. Pedestrians are also asked to please keep to posted sidewalks for their safety around construction traffic.

  • Drop-in Information Sessions

    Share Drop-in Information Sessions on Facebook Share Drop-in Information Sessions on Twitter Share Drop-in Information Sessions on Linkedin Email Drop-in Information Sessions link
    supporting image

    Planning of the Red Deer Regional Hospital Centre (RDRHC) Redevelopment Project is well underway, with multiple activities occurring within the site which will become the norm as we execute this project over the next several years.

    Everyone will start seeing a variety of construction workers, designers and engineers throughout the facility that we are not accustomed to seeing on a usual basis. In addition to providing advanced notification to impacted areas about this increased activity, AHS' Project Team is offering a series of information sessions for staff, physicians and volunteers to share an overview of the project, where we’re at, and where we’re going. Drop-in sessions being offered on these dates:

    • Tuesday, August 6
    • Thursday, August 8
    • Friday, August 16

    Sessions will be offered from 11 a.m. to 11:30 a.m., noon to 12:30 p.m. and from 1 p.m. to 1:30 p.m. in Dining Room B. Members of the Project Team will be on hand to answer questions.


  • Schematic design flyover

    Share Schematic design flyover on Facebook Share Schematic design flyover on Twitter Share Schematic design flyover on Linkedin Email Schematic design flyover link
    supporting image

    During their March 14 Information Session on the Project, Alberta Infrastructure shared schematic design drawings of the new patient tower portion of the Project, as well as a video simulating a flyover of the new tower and new power plant. You can view the flyover video here:


  • Alberta Infrastructure Hosting Public Information Session

    Share Alberta Infrastructure Hosting Public Information Session on Facebook Share Alberta Infrastructure Hosting Public Information Session on Twitter Share Alberta Infrastructure Hosting Public Information Session on Linkedin Email Alberta Infrastructure Hosting Public Information Session link

    Alberta Infrastructure is hosting a public information session to provide updates on the Red Deer Hospital expansion project:

    • March 14, 2024, 7 p.m. – 9 p.m.
    • The Chalet, Westerner Park, 4847A 19 Street, Red Deer
    • Project representatives will be on hand to answer questions.
  • Project Timeline

    Share Project Timeline on Facebook Share Project Timeline on Twitter Share Project Timeline on Linkedin Email Project Timeline link

  • Building Forward, Together

    Share Building Forward, Together on Facebook Share Building Forward, Together on Twitter Share Building Forward, Together on Linkedin Email Building Forward, Together link

    Staff and physicians are invited to come learn more about the RDRHC redevelopment transition planning work with site and Zone leadership.

    When June 26 and 27, 2023

    Time: 7:30 a.m. to 7:30 p.m.

    Where: Critical Care Link (2nd floor)

    Drop-in style

  • Public Information Session

    Share Public Information Session on Facebook Share Public Information Session on Twitter Share Public Information Session on Linkedin Email Public Information Session link

    Community members are invited to a public information session to learn more about the complex building process, and the roles of the Ministry of Infrastructure, Ministry of Health and Alberta Health Services (AHS) in capital project delivery.

    January 26, 2023